How the Power Actually Gets There
The four routes

The electricity exists.
Getting to it is the problem.

A data center needs power and somewhere a generator makes power. Everything hard about this subject lives in between: the queue, the wire, the contract and the permission. There are exactly four ways to join the two, they take wildly different amounts of time, and only two of them add any electricity to the system at all. This page is about the gap and the four ways across it.

Read this part
Everything here carries a date, and the date is part of the claim. The rules described on this page were made recently and are still being written: the co-location framework in PJM was ordered in December 2025 and was still in compliance proceedings in 2026, and the federal process for connecting large loads did not exist at all until FERC acted in June 2026. Figures were verified in August 2026 against Lawrence Berkeley National Laboratory, FERC orders, EIA and grid operator filings. If a decision turns on any of it, read the underlying order or filing rather than this summary.
ON THIS PAGE
The Gap, Stated Plainly Where the Load Actually Is What Is Planned, and How Firm It Is The Four Routes Route Two: The Generator Queue Route One: The Queue Nobody Had a Process For Route Three: Sitting Next to the Plant Route Four: Buying What Already Exists Who Pays for the Wire The Answer Most Developers Actually Chose Where Small Modular Reactors Fit How to Read a Claim About This Where This Comes From
Two things that both exist, and do not touch

The Gap, Stated Plainly

A data center needs electricity. Somewhere there is a generator that makes electricity. Those two facts are the easy part, and almost every article on this subject treats them as the whole story. They are not. The hard part is the connection between them, and the connection is where the years go, where the money goes, and where nearly all of the confusion lives.

Here is the thing worth holding on to before anything else. Electricity is not a commodity you can put on a truck. It has to travel down a wire that someone built, under a contract someone signed, with permission from a regulator who had to approve both. A megawatt that exists in Pennsylvania and a server hall in Virginia that wants it are not connected by wanting.

Two questions that sound the same and are not
Is there enough electricity? A question about generation, and its answer is reasonably encouraging. The US grid has spare energy at most hours of most days, and the 2026 build is a record: about 43.4 GW of solar, 24 GW of battery storage and 6.3 GW of gas in an 86 GW year. Storage matters most here, because it is what turns variable output into something a flat load can lean on. Generation
Can this load reach it? A question about connection, and its answer is much worse. The wire, the contract and the permission are three separate problems, and a generator reaching commercial operation in 2025 waited a median of 61 months. Connection

Nearly every dispute in this subject is the second question dressed in the language of the first. When a utility says it cannot serve a campus, it is rarely saying the electricity does not exist. It is saying it cannot get it there, on the schedule asked for, without building something.

It does not spread out. It clusters, and the clusters are enormous

Where the Load Actually Is

Data center demand is not a national average sprinkled evenly across the country. It arrives as a small number of very large campuses in a small number of places, and that concentration is the reason a national statistic about spare generating capacity tells you almost nothing about whether any particular campus can be served.

Two different numbers, both called "capacity"
IT power is the chips and the equipment directly attached to them. Total facility power is that plus cooling, power conversion and everything else, and it is roughly IT power multiplied by the facility's power usage effectiveness. Independent measurement reports IT power. Company announcements almost always describe eventual total facility power, years out. The two are not the same number, and confusing them is the single largest source of error in coverage of this subject.
The largest US campuses, measured IT power in megawatts. Solid = measured Aug 2026. Outline = projected. Epoch AI, built from satellite imagery, construction permits and public documents IT power is chips and directly associated equipment. Total facility power is higher, which is why announced figures are larger. Colossus 2 xAI, Memphis TN 946 MW 1,531 MW Q1 2027 New Carlisle Amazon, New Carlisle IN 910 MW 1,925 MW Q1 2028 Fairwater Atlanta Microsoft, Fayetteville GA 636 MW no projection Prometheus Meta, New Albany OH 562 MW 854 MW Q1 2027 Google New Albany Google, New Albany OH 453 MW no projection Stargate Abilene Oracle/OpenAI, Abilene TX 421 MW 843 MW Q4 2026 Colossus 1 xAI, Memphis TN 340 MW no projection Hyperion Meta, Richland Parish LA not yet operating 1,676 MW Q1 2028 Company announcements describe eventual TOTAL FACILITY power; these bars are measured IT power. The two are different numbers, and the gap between them is the largest single source of confusion in coverage of this subject.
The largest US campuses by measured IT power against projected IT power. Epoch AI's open database, built from satellite imagery, construction permits and public documents, covering 83 sites and about 13 GW of IT power, last updated 24 August 2026. Individual readings are dated between March and August 2026. Epoch notes that total facility power runs 20 to 50 percent above IT power.
Campus Where Measured IT power Power source
Colossus 2 Memphis, TN 946 MW (June 2026). Projected 1,531 by Q1 2027 On-site gas turbines, sited in Southaven, MS
New Carlisle New Carlisle, IN 910 MW (March 2026). Projected 1,925 by Q1 2028 Grid, with backup diesel
Fairwater Atlanta Fayetteville, GA 636 MW (June 2026) Grid
Prometheus New Albany, OH 562 MW (August 2026). Projected 854 by Q1 2027 On-site gas
Google New Albany New Albany, OH 453 MW (August 2026) Grid
Stargate Abilene Abilene, TX 421 MW (May 2026), four of eight buildings On-site gas turbines and a 1 GW substation
Fairwater Wisconsin Mount Pleasant, WI 369 MW Grid
Google Pryor (North) Pryor, OK 368 MW Grid
Read the dates in that column
The database was last updated on 24 August 2026, but the individual readings are not all from August — they range from March to August 2026, and a campus under active construction can gain hundreds of megawatts between readings. A measured figure is a photograph of a moving thing. It is still far better than an announcement, which is a photograph of an intention.

Note the right-hand column, because it answers the question this page is about more directly than anything else on it. Of the eight largest operating campuses in the country, three generate power on their own site, and in every one of those cases the fuel is natural gas. The rest take grid power. None of them is served by a small modular reactor, because there is not one to be served by.

Meta's Hyperion in Richland Parish, Louisiana, is missing from that table on purpose. It is the largest campus in the country by announced capacity and it measures nothing at all, because it is still under construction. It belongs in the next section rather than this one, and keeping the two apart is the whole discipline of this page.

What a gigawatt is, in two comparisons
One gigawatt running continuously for a year is about 8,760 gigawatt-hours, roughly the annual electricity of 810,000 average US homes. It is also about one large reactor: Vogtle Unit 4 is 1,114 MW. Be careful which comparison you are making, though — the homes figure is an energy comparison at full output. Homes peak in the early evening and a data center runs nearly flat, so measured against residential peak demand the ratio is much smaller. Quoting the energy ratio as if it were a capacity ratio overstates the comparison considerably.
The pipeline is real, enormous, and mostly at the softest possible stage

What Is Planned, and How Firm It Is

Announced campuses are much larger than operating ones, and they are announced in total facility power at full build-out, which is typically several years and several construction phases away. Both things can be true at once: the pipeline is genuinely large, and the headline numbers are the softest figures in the subject.

Announced campus Where Announced capacity Status, Aug 2026
Meta Hyperion Richland Parish, LA 5 GW at full build-out, ~2,250 acres Under construction. 1.5 GW targeted end-2027, build through 2030
Stargate Doña Ana County Doña Ana County, NM 2.2 GW Under construction, on-site gas
Stargate Shackelford County Shackelford County, TX 2.0 GW Under construction, on-site gas
Stargate Saline Township Saline Township, MI 1.4 GW Under construction, grid plus battery storage
Stargate Port Washington Port Washington, WI 1.3 GW Under construction, grid plus renewables
Stargate Milam County Milam County, TX 1.2 GW Under construction, on-site generation
Stargate Abilene Abilene, TX 1.2 GW capped campus figure Partially operating, four of eight buildings
Stargate Lordstown Lordstown, OH Under 0.3 GW Announced, early stage

The site capacities in that table come from Epoch AI's April 2026 review of where the Stargate sites stand, and they sum to about 9.6 GW. Treat the total with the same suspicion as any other announced figure: OpenAI's own release describes the program as nearly 7 gigawatts of planned capacity and describes two of the sites jointly rather than separately. When the developer and the analyst disagree about the total, both numbers are announcements. For scale: Hyperion at its announced 5 GW would be comparable to the entire Plant Vogtle site in Georgia, which at close to 5 GW is the largest nuclear plant in the United States and took from 2009 to 2024 and more than $30 billion to expand.

How far apart announced and measured can be
What was announced xAI's Colossus across Memphis and Southaven was reported in January 2026 as "roughly 2 gigawatts and more than 555,000 GPUs". Company
What is measured Epoch's measured IT power for Colossus 1 and Colossus 2 together was 1,286 MW in August 2026. Independent

Neither figure is dishonest. The announcement describes total facility power at an intended end state; the measurement describes IT power now. But they are routinely quoted side by side as though they were the same quantity, and a reader who does not know the difference will conclude that half the capacity has gone missing.

The most useful public illustration of how soft a pipeline figure can be comes from a utility rather than a developer. Dominion Energy Virginia disclosed 53.8 GW of data center capacity under contract in July 2026, up from 16.5 GW three years earlier. It also broke that figure into stages, which almost nobody else does.

Dominion Energy Virginia, July 2026 Capacity How firm
Early substation engineering letter of authorization 32.4 GW The softest stage. An intention with an engineering study attached
Construction letter of authorization 9.4 GW Further along, and construction has been authorized
Firm electric service agreements 12.0 GW Carries revenue commitments whether or not the customer takes service
The number to quote, and the number people quote
Of Dominion's 53.8 GW headline, 12.0 GW is contractually firm. The rest is real interest at earlier stages, and some of it will not happen. When you see a utility or a region quoted with a large contracted figure and no stage breakdown, assume it is the 53.8 and not the 12.0.

The speed of revision is its own warning. Georgia Power's projected incremental load over roughly seven years went from 400 MW in its 2022 filing to 6,600 MW in 2023 and 8,500 MW in 2024. That is a twenty-one-fold revision at one utility inside three years, and it is the cleanest single illustration of how uncertain these forecasts are — in both directions.

The procurement followed. On 19 December 2025 the Georgia Public Service Commission certified resources totalling 9,885 MW with commercial operation or delivery dates between 2027 and 2030, a figure Georgia Power has said is expected to serve data centers to the extent of roughly 80 percent. Note that certifying resources is not the same as building generation — it covers purchases and contracts too — and note the scale: Georgia Power's entire existing statewide capacity is around 22,000 MW.

Every arrangement in this subject is one of these

The Four Routes

There are four ways to join a data center to a source of electricity, and every arrangement in this subject is one of them or a combination of them. They are not variations on a theme. They differ in who waits, who pays, who approves it, and — the difference that matters most and gets mentioned least — whether any new electricity exists at the end.

THE LOAD A data center THE SOURCE A generator Four ways to join them and what each one actually costs you Route 1 · The load joins the queue No published median Large-load interconnection was a state matter with no national process until FERC opened one. ERCOT alone held ~474 GW of requests in Aug 2026. adds no supply Route 2 · Build a generator, join the queue 61 months median That is the 2025 median for a generator reaching commercial operation. Of capacity queued 2000-2020, 13% was built and 75% withdrawn. adds supply Route 3 · Generation on your own site Permitted, with a rulebook Co-locate beside an existing plant, or build your own. FERC rejected the Susquehanna deal in Nov 2024 and made PJM write rules in Dec 2025. adds supply only if the plant is new Route 4 · Contract for existing output Signable today Fastest by far, and it adds no electricity to the system. All 8.3 GW under contract to technology companies comes from reactors that already exist. adds no supply
The four routes, with the wait and the catch on each. One always adds supply to the system, two never do, and one depends on whether the generator on your site is a new plant or one that was already running. Sources: Lawrence Berkeley National Laboratory (Queued Up, 2026 edition) for queue duration and completion; ERCOT and the Texas Tribune for the large-load request total, August 2026; FERC orders of November 2024, December 2025 and April 2026 for co-location; contracted capacity summed from the six announced technology company agreements.
The distinction the whole page turns on
Routes 2 and 3 can add electricity to the system, because at the end of them a generator exists that did not exist before. Routes 1 and 4 move electricity that already exists to a different buyer. Both kinds are legitimate and both are commonly announced in identical language. A contract for the output of an existing reactor does not add a single megawatt-hour to the country's supply. It changes whose name is on it.

That is not a criticism of the contracts. They are real, they are large, and they keep existing plants running that might otherwise have closed — which has genuine value. It is a criticism of how they are described, because "powering AI with nuclear" is used for both kinds without distinction, and only one of them changes what the country can generate.

Why building the supply is a five-year proposition

Route Two: The Generator Queue

If you want a new power plant to serve the grid, it joins an interconnection queue. The grid operator studies what your plant does to the system, works out what has to be reinforced, assigns you the cost, and eventually offers an agreement. This process is federally regulated and reasonably well documented, which is why it is the part of this story people can actually cite numbers for.

How long a generator waits Median months, interconnection request to commercial operation Lawrence Berkeley National Laboratory, Queued Up, 2026 edition Online 2008 22 months Online 2015 36 months Online 2025 61 months This is the queue for GENERATORS. Data centers are loads, and loads sit in separate queues that this report does not cover. Quoting 61 months as a data center wait misuses it.
Median months from interconnection request to commercial operation, by the year the plant came online. Lawrence Berkeley National Laboratory, Queued Up, 2026 edition. The caveat in the figure is the report's own: these are generator queues, and large loads are counted separately.
The generator queue Lawrence Berkeley, 2026 edition
Capacity waiting at the end of 2025 ~2,061 GW active
Median request to commercial operation, 2008 22 months
Median request to commercial operation, 2025 61 months, about five years
Of capacity queued 2000–2020, how much was built 13%. 75% was withdrawn
By project count rather than capacity 19% reached commercial operation
Withdrawal even after signing an agreement 41% of capacity, 2000–2022

The last three rows are the ones that change behavior. A developer who plans around a specific queued plant is planning around something with roughly a one in eight chance of existing — and signing the interconnection agreement does not settle it, because two fifths of the capacity that got that far still withdrew. That is the counterparty risk that makes building your own generation look reasonable rather than eccentric.

What the 61 months does and does not measure
How it is quoted As "how long a data center waits to get connected", usually rounded to a flat five years and usually with no source attached at all. The misuse
What the report says Queued Up states plainly that its data covers only resources that supply electricity to the grid, and that large loads are in separate queues not included in the report. It measures how long a generator waits. The source

Both facts are real and they are about different things. A data center is a load. The generator queue matters to it enormously, because it is why the supply it wants is slow to arrive, but the 61 months is not its own wait. Anyone quoting it as a data center connection time, in either direction, is misusing the source.

Connecting a very large load was a state matter with no national standard

Route One: The Queue Nobody Had a Process For

The ordinary route is the one nobody writes about: the data center asks the utility for service, like any other customer, and takes power from the grid. For a load the size of a small city, that turns out to be a much less settled process than connecting a power plant.

Meanwhile the request volumes are extraordinary, and they are the single weakest number in this entire subject. ERCOT reported roughly 474 GW of large-load interconnection requests in August 2026, about 90 percent of them data centers, against a record actual peak of about 85.5 GW set in August 2023. The Governor of Texas ordered an audit of those projects on 3 August 2026, covering whether they bring their own generation, where their water comes from, and what public assistance they have received.

Why a request total is not a demand forecast
A developer shopping one campus to five utilities generates five requests for one data center. Nobody has lied; each utility sees real demand; the system counts it five times. Wood Mackenzie reported in August 2026 that US grid operators and utilities had received requests totalling 1,066 GW for data center projects — about 83 percent of the entire US utility-scale generating fleet, which stood near 1,281 GW at the end of 2025 — and expects operators to commit to roughly 28 percent of it. Treat a queue total as evidence of intent and of duplication in unknown proportions, never as a forecast of load.

There is a real signal underneath the noise, and it points the other way from the headline. PJM cut its summer 2028 peak forecast by 4,414 megawatts, about 2.6 percent, citing stricter vetting of planned data centers and large loads. When an operator starts checking, the number goes down.

The idea that seemed obvious, and the eighteen months it took to settle

Route Three: Sitting Next to the Plant

If the wire is the problem, remove the wire. Put the data center on the same site as the generator, run a short private connection, and never touch the public grid: no queue, no transmission charges, no waiting. This is called behind-the-meter co-location, and for about two years it was widely assumed to be the answer.

  1. 1
    November 2024 — FERC says no
    Amazon had bought a 300 MW data center campus physically co-located at Talen's Susquehanna nuclear plant in Pennsylvania, and PJM filed an amended interconnection agreement to expand it. FERC rejected the filing two to one, finding the non-standard terms had not been justified. Rehearing was denied in April 2025.
  2. 2
    June 2025 — the market answers before the regulator finishes
    Rather than keep litigating, Amazon and Talen restructured the whole arrangement to front-of-the-meter: Susquehanna sells into PJM, Talen acts as Amazon's retail supplier, and the local utility handles delivery. The largest co-located nuclear data center in America de-co-located itself and accepted grid charges.
  3. 3
    December 2025 — FERC writes a rulebook
    FERC found PJM's tariff unjust and unreasonable for lack of clarity, and ordered it to create four defined transmission service options for co-located load, along with reforms to behind-the-meter netting rules.
  4. 4
    April 2026 — partially settled
    FERC accepted some of PJM's compliance filings and rejected others, notably PJM's attempt to narrow the definition of co-located load. Questions about pairing with storage, and about how the costs are allocated, remain open.
What it settles
Co-location in PJM is now permitted with a rulebook rather than prohibited, which is a better outcome for the industry than the November 2024 headline suggested. But the version people imagined — unplug from the grid, plug into the reactor, pay nothing for transmission — is dead there. A data center can sit beside a reactor, but it takes one of four defined service products and pays accordingly.

The reason regulators care is not obstruction. A plant that served every customer on the system and now serves one customer has left the common pool, while in practice still relying on the grid to back it up when the unit trips or refuels. Somebody pays for that backup and for the transmission that provides it. Deciding who is a real question, not a delaying tactic.

The fastest route, and the one that adds nothing

Route Four: Buying What Already Exists

The fourth route skips construction entirely. Find a reactor that is already running, or one that has been shut down and could be restarted, and sign a long-term contract for its output. This is the route almost every famous deal in this subject has actually taken.

Buyer and seller Plant MW Status
Microsoft / Constellation Crane Clean Energy Center, formerly Three Mile Island 1, PA 835 Not yet operating. Restart targeted 2027
Amazon / Talen Susquehanna, PA up to 1,920 Operating
Meta / Constellation Clinton, IL 1,121 Operating, deliveries from June 2027
Meta / Vistra Perry, Davis-Besse, Beaver Valley 2,609 Operating
Amazon / Vistra Comanche Peak, TX 1,200 Operating
Google / NextEra Duane Arnold, IA 615 Not yet operating. Restart targeted Q1 2029

8.3 GW across six contracts, with named plants and named sellers. This is a real and substantial market. Every megawatt of it comes from a reactor that already exists or one being brought back from retirement, and none of it is a small modular reactor.

Two things a contract can buy, and they are not the same
The electricity An offtaker agrees to buy a plant's output on defined terms for a defined period: physical power, with a price and a penalty for non-performance. The electrons
The clean energy attributes The environmental characteristics of the generation, bought separately from the power itself. A company can buy the attributes of a plant whose electricity goes to somebody else entirely. The claim

The clearest worked example is the only signed small modular reactor agreement in the country. The Tennessee Valley Authority agreed in August 2025 to buy up to 50 MW from Kairos Power's Hermes 2 plant at Oak Ridge, with Google taking the clean energy attributes for data centers in Tennessee and Alabama. The power goes to the TVA grid. Both descriptions of that deal are true, and only one of them means what a casual reader assumes.

Note also what the restart deals reveal about the timescale. Two of the six contracts are for plants that have not restarted yet. Three Mile Island Unit 1 is targeted for 2027; Duane Arnold for the first quarter of 2029. Restarting a reactor that already exists, on a licensed site, with the transmission already built, is the fastest way to add firm capacity anyone has found — and it still takes years.

The question underneath every regulatory fight on this page

Who Pays for the Wire

Connecting a very large load usually means building something: a substation, a transmission upgrade, sometimes a line. That cost is real and somebody is assigned it. Every co-location dispute, every large-load rulemaking and every state proceeding on this subject is, underneath, an argument about who.

States have started writing the answer into the tariff rather than arguing it case by case. Georgia is the most developed example: the Public Service Commission ordered a base rate freeze through 2028 in July 2025, imposed minimum billing and longer contract terms on large loads, required new data center contracts to be filed thirty days before execution, and required Georgia Power to backstop the costs financially through 2031 if the contracts do not materialize.

What to look for in any deal announcement
A serious arrangement says who pays for the interconnection, what happens if the load arrives smaller or later than promised, and whether the load can be curtailed when the system is short. An announcement that mentions none of those three is describing an intention, not a transaction.
It is not nuclear, and it is already being built

The Answer Most Developers Actually Chose

Faced with four routes that are all slow or constrained, a great many developers took the most aggressive version of route 3: not co-locating beside somebody else's plant, but building their own generation on site and waiting for nobody. That generation is overwhelmingly natural gas, not nuclear, and it is happening now rather than in the 2030s. It is also the version of route 3 that genuinely adds supply, because the plant is new.

Even this has a queue of its own, just not a regulatory one. Gas turbines are sold out. As of manufacturer earnings reported in August 2026, GE Vernova held a 116 GW backlog with delivery slots into 2031; Siemens Energy quoted about three years and held 69 GW; Mitsubishi held 35 GW. Order intake is running three to seven times shipment rate, which is what a sold-out factory looks like.

Why this matters for reading the nuclear story
The nuclear announcements are competing for attention with something that is being poured in concrete right now. If you want to know what is actually bridging the gap between AI demand and electricity supply in 2026, the honest answer is gas turbines, grid contracts on existing reactors, and a great deal of solar and storage — not small modular reactors, which have not connected a single data center anywhere.
The bridge they would be, if one existed

Where Small Modular Reactors Fit

The case for a small modular reactor next to a data center is a connection argument, not a generation argument. It is not that nuclear electricity is cheaper — it is not. It is that a reactor on your own site is route 3 in its supply-adding form, and it sidesteps both queues at once: no waiting for the grid to reach you, and no waiting for somebody else's plant to be built. It is the same argument that put gas turbines on eight campuses, with a different fuel.

That is a coherent argument. The difficulty is entirely in the present tense. As of August 2026, no small modular reactor is operating anywhere in the United States, and none is under construction with a data center as its contracted customer. The two most advanced construction permit applications in the country are TVA's Clinch River, for the Tennessee Valley grid, and X-energy's Long Mott, for a Dow chemical works at Seadrift, Texas. Neither is an AI project.

Route Time to first electricity Adds supply?
Contract for an operating reactor Months. The plant is already running No
Restart a shut-down reactor Years. Nothing has restarted yet in the US Yes
Uprate an existing plant Years, but the licence and connection exist Yes
Build gas on site Years, and turbine slots run into 2031 Yes
Build a small modular reactor Not yet demonstrated anywhere in the US Yes

This is why the sector's own scoreboard is worth watching more closely than its announcements. The thing that would change this picture is not another framework agreement. It is a construction permit application that names a data center as the customer, or an operating licence application from one of the companies already building. Neither had happened by August 2026.

Four routes, four different sentences, one press release

How to Read a Claim About This

Almost every misleading claim in this subject comes from describing one route in language borrowed from another. The decoder is short. When you read that a company is powering AI with some source of electricity, work out which of the four routes is being described, and then ask the question in the right-hand column.

If the claim sounds like It is probably Ask
"We signed an agreement for X gigawatts" Route 4, or nothing at all Is there a named plant, a named seller and a stated term? Or is it a framework?
"We are building a plant to power our data centers" Route 2 or 3 Which regulatory instrument has been granted, and on what date?
"Powered by carbon-free energy" Possibly attributes, not electricity Do the electrons go to this company, or only the clean energy attributes?
"We will bypass the grid entirely" Route 3, described as it was in 2024 Which of the four co-located service products, and what is being paid?
"The grid cannot support this" A connection claim, not a generation claim Is the shortage energy, or capacity at the peak, or a wire that does not exist?
The one-sentence version
The queue is the bridge that exists and it is slow; putting generation on your own site is the attempt to go around it, and it now has a rulebook; a purchase agreement is the contract that makes any of it real; and building your own gas plant is what most developers actually did while the other routes were being argued about.
And which parts will go stale first

Where This Comes From

What will age fastest
The co-location rules, because they are actively in compliance proceedings and the questions on storage pairing and cost allocation were still open in 2026. The large-load federal process, because the six show-cause responses FERC ordered on 18 June 2026 were due within sixty days and what those markets propose is not yet known. And the request totals, which move every quarter and are the least reliable numbers on the page even when they are quoted correctly.