A data center needs power and somewhere a generator makes power. Everything hard about this subject lives in between: the queue, the wire, the contract and the permission. There are exactly four ways to join the two, they take wildly different amounts of time, and only two of them add any electricity to the system at all. This page is about the gap and the four ways across it.
A data center needs electricity. Somewhere there is a generator that makes electricity. Those two facts are the easy part, and almost every article on this subject treats them as the whole story. They are not. The hard part is the connection between them, and the connection is where the years go, where the money goes, and where nearly all of the confusion lives.
Here is the thing worth holding on to before anything else. Electricity is not a commodity you can put on a truck. It has to travel down a wire that someone built, under a contract someone signed, with permission from a regulator who had to approve both. A megawatt that exists in Pennsylvania and a server hall in Virginia that wants it are not connected by wanting.
| Is there enough electricity? | A question about generation, and its answer is reasonably encouraging. The US grid has spare energy at most hours of most days, and the 2026 build is a record: about 43.4 GW of solar, 24 GW of battery storage and 6.3 GW of gas in an 86 GW year. Storage matters most here, because it is what turns variable output into something a flat load can lean on. | Generation |
| Can this load reach it? | A question about connection, and its answer is much worse. The wire, the contract and the permission are three separate problems, and a generator reaching commercial operation in 2025 waited a median of 61 months. | Connection |
Nearly every dispute in this subject is the second question dressed in the language of the first. When a utility says it cannot serve a campus, it is rarely saying the electricity does not exist. It is saying it cannot get it there, on the schedule asked for, without building something.
Data center demand is not a national average sprinkled evenly across the country. It arrives as a small number of very large campuses in a small number of places, and that concentration is the reason a national statistic about spare generating capacity tells you almost nothing about whether any particular campus can be served.
| Campus | Where | Measured IT power | Power source |
|---|---|---|---|
| Colossus 2 | Memphis, TN | 946 MW (June 2026). Projected 1,531 by Q1 2027 | On-site gas turbines, sited in Southaven, MS |
| New Carlisle | New Carlisle, IN | 910 MW (March 2026). Projected 1,925 by Q1 2028 | Grid, with backup diesel |
| Fairwater Atlanta | Fayetteville, GA | 636 MW (June 2026) | Grid |
| Prometheus | New Albany, OH | 562 MW (August 2026). Projected 854 by Q1 2027 | On-site gas |
| Google New Albany | New Albany, OH | 453 MW (August 2026) | Grid |
| Stargate Abilene | Abilene, TX | 421 MW (May 2026), four of eight buildings | On-site gas turbines and a 1 GW substation |
| Fairwater Wisconsin | Mount Pleasant, WI | 369 MW | Grid |
| Google Pryor (North) | Pryor, OK | 368 MW | Grid |
Note the right-hand column, because it answers the question this page is about more directly than anything else on it. Of the eight largest operating campuses in the country, three generate power on their own site, and in every one of those cases the fuel is natural gas. The rest take grid power. None of them is served by a small modular reactor, because there is not one to be served by.
Meta's Hyperion in Richland Parish, Louisiana, is missing from that table on purpose. It is the largest campus in the country by announced capacity and it measures nothing at all, because it is still under construction. It belongs in the next section rather than this one, and keeping the two apart is the whole discipline of this page.
Announced campuses are much larger than operating ones, and they are announced in total facility power at full build-out, which is typically several years and several construction phases away. Both things can be true at once: the pipeline is genuinely large, and the headline numbers are the softest figures in the subject.
| Announced campus | Where | Announced capacity | Status, Aug 2026 |
|---|---|---|---|
| Meta Hyperion | Richland Parish, LA | 5 GW at full build-out, ~2,250 acres | Under construction. 1.5 GW targeted end-2027, build through 2030 |
| Stargate Doña Ana County | Doña Ana County, NM | 2.2 GW | Under construction, on-site gas |
| Stargate Shackelford County | Shackelford County, TX | 2.0 GW | Under construction, on-site gas |
| Stargate Saline Township | Saline Township, MI | 1.4 GW | Under construction, grid plus battery storage |
| Stargate Port Washington | Port Washington, WI | 1.3 GW | Under construction, grid plus renewables |
| Stargate Milam County | Milam County, TX | 1.2 GW | Under construction, on-site generation |
| Stargate Abilene | Abilene, TX | 1.2 GW capped campus figure | Partially operating, four of eight buildings |
| Stargate Lordstown | Lordstown, OH | Under 0.3 GW | Announced, early stage |
The site capacities in that table come from Epoch AI's April 2026 review of where the Stargate sites stand, and they sum to about 9.6 GW. Treat the total with the same suspicion as any other announced figure: OpenAI's own release describes the program as nearly 7 gigawatts of planned capacity and describes two of the sites jointly rather than separately. When the developer and the analyst disagree about the total, both numbers are announcements. For scale: Hyperion at its announced 5 GW would be comparable to the entire Plant Vogtle site in Georgia, which at close to 5 GW is the largest nuclear plant in the United States and took from 2009 to 2024 and more than $30 billion to expand.
| What was announced | xAI's Colossus across Memphis and Southaven was reported in January 2026 as "roughly 2 gigawatts and more than 555,000 GPUs". | Company |
| What is measured | Epoch's measured IT power for Colossus 1 and Colossus 2 together was 1,286 MW in August 2026. | Independent |
Neither figure is dishonest. The announcement describes total facility power at an intended end state; the measurement describes IT power now. But they are routinely quoted side by side as though they were the same quantity, and a reader who does not know the difference will conclude that half the capacity has gone missing.
The most useful public illustration of how soft a pipeline figure can be comes from a utility rather than a developer. Dominion Energy Virginia disclosed 53.8 GW of data center capacity under contract in July 2026, up from 16.5 GW three years earlier. It also broke that figure into stages, which almost nobody else does.
| Dominion Energy Virginia, July 2026 | Capacity | How firm |
|---|---|---|
| Early substation engineering letter of authorization | 32.4 GW | The softest stage. An intention with an engineering study attached |
| Construction letter of authorization | 9.4 GW | Further along, and construction has been authorized |
| Firm electric service agreements | 12.0 GW | Carries revenue commitments whether or not the customer takes service |
The speed of revision is its own warning. Georgia Power's projected incremental load over roughly seven years went from 400 MW in its 2022 filing to 6,600 MW in 2023 and 8,500 MW in 2024. That is a twenty-one-fold revision at one utility inside three years, and it is the cleanest single illustration of how uncertain these forecasts are — in both directions.
The procurement followed. On 19 December 2025 the Georgia Public Service Commission certified resources totalling 9,885 MW with commercial operation or delivery dates between 2027 and 2030, a figure Georgia Power has said is expected to serve data centers to the extent of roughly 80 percent. Note that certifying resources is not the same as building generation — it covers purchases and contracts too — and note the scale: Georgia Power's entire existing statewide capacity is around 22,000 MW.
There are four ways to join a data center to a source of electricity, and every arrangement in this subject is one of them or a combination of them. They are not variations on a theme. They differ in who waits, who pays, who approves it, and — the difference that matters most and gets mentioned least — whether any new electricity exists at the end.
That is not a criticism of the contracts. They are real, they are large, and they keep existing plants running that might otherwise have closed — which has genuine value. It is a criticism of how they are described, because "powering AI with nuclear" is used for both kinds without distinction, and only one of them changes what the country can generate.
If you want a new power plant to serve the grid, it joins an interconnection queue. The grid operator studies what your plant does to the system, works out what has to be reinforced, assigns you the cost, and eventually offers an agreement. This process is federally regulated and reasonably well documented, which is why it is the part of this story people can actually cite numbers for.
| The generator queue | Lawrence Berkeley, 2026 edition |
|---|---|
| Capacity waiting at the end of 2025 | ~2,061 GW active |
| Median request to commercial operation, 2008 | 22 months |
| Median request to commercial operation, 2025 | 61 months, about five years |
| Of capacity queued 2000–2020, how much was built | 13%. 75% was withdrawn |
| By project count rather than capacity | 19% reached commercial operation |
| Withdrawal even after signing an agreement | 41% of capacity, 2000–2022 |
The last three rows are the ones that change behavior. A developer who plans around a specific queued plant is planning around something with roughly a one in eight chance of existing — and signing the interconnection agreement does not settle it, because two fifths of the capacity that got that far still withdrew. That is the counterparty risk that makes building your own generation look reasonable rather than eccentric.
| How it is quoted | As "how long a data center waits to get connected", usually rounded to a flat five years and usually with no source attached at all. | The misuse |
| What the report says | Queued Up states plainly that its data covers only resources that supply electricity to the grid, and that large loads are in separate queues not included in the report. It measures how long a generator waits. | The source |
Both facts are real and they are about different things. A data center is a load. The generator queue matters to it enormously, because it is why the supply it wants is slow to arrive, but the 61 months is not its own wait. Anyone quoting it as a data center connection time, in either direction, is misusing the source.
The ordinary route is the one nobody writes about: the data center asks the utility for service, like any other customer, and takes power from the grid. For a load the size of a small city, that turns out to be a much less settled process than connecting a power plant.
Meanwhile the request volumes are extraordinary, and they are the single weakest number in this entire subject. ERCOT reported roughly 474 GW of large-load interconnection requests in August 2026, about 90 percent of them data centers, against a record actual peak of about 85.5 GW set in August 2023. The Governor of Texas ordered an audit of those projects on 3 August 2026, covering whether they bring their own generation, where their water comes from, and what public assistance they have received.
There is a real signal underneath the noise, and it points the other way from the headline. PJM cut its summer 2028 peak forecast by 4,414 megawatts, about 2.6 percent, citing stricter vetting of planned data centers and large loads. When an operator starts checking, the number goes down.
If the wire is the problem, remove the wire. Put the data center on the same site as the generator, run a short private connection, and never touch the public grid: no queue, no transmission charges, no waiting. This is called behind-the-meter co-location, and for about two years it was widely assumed to be the answer.
The reason regulators care is not obstruction. A plant that served every customer on the system and now serves one customer has left the common pool, while in practice still relying on the grid to back it up when the unit trips or refuels. Somebody pays for that backup and for the transmission that provides it. Deciding who is a real question, not a delaying tactic.
The fourth route skips construction entirely. Find a reactor that is already running, or one that has been shut down and could be restarted, and sign a long-term contract for its output. This is the route almost every famous deal in this subject has actually taken.
| Buyer and seller | Plant | MW | Status |
|---|---|---|---|
| Microsoft / Constellation | Crane Clean Energy Center, formerly Three Mile Island 1, PA | 835 | Not yet operating. Restart targeted 2027 |
| Amazon / Talen | Susquehanna, PA | up to 1,920 | Operating |
| Meta / Constellation | Clinton, IL | 1,121 | Operating, deliveries from June 2027 |
| Meta / Vistra | Perry, Davis-Besse, Beaver Valley | 2,609 | Operating |
| Amazon / Vistra | Comanche Peak, TX | 1,200 | Operating |
| Google / NextEra | Duane Arnold, IA | 615 | Not yet operating. Restart targeted Q1 2029 |
8.3 GW across six contracts, with named plants and named sellers. This is a real and substantial market. Every megawatt of it comes from a reactor that already exists or one being brought back from retirement, and none of it is a small modular reactor.
| The electricity | An offtaker agrees to buy a plant's output on defined terms for a defined period: physical power, with a price and a penalty for non-performance. | The electrons |
| The clean energy attributes | The environmental characteristics of the generation, bought separately from the power itself. A company can buy the attributes of a plant whose electricity goes to somebody else entirely. | The claim |
The clearest worked example is the only signed small modular reactor agreement in the country. The Tennessee Valley Authority agreed in August 2025 to buy up to 50 MW from Kairos Power's Hermes 2 plant at Oak Ridge, with Google taking the clean energy attributes for data centers in Tennessee and Alabama. The power goes to the TVA grid. Both descriptions of that deal are true, and only one of them means what a casual reader assumes.
Note also what the restart deals reveal about the timescale. Two of the six contracts are for plants that have not restarted yet. Three Mile Island Unit 1 is targeted for 2027; Duane Arnold for the first quarter of 2029. Restarting a reactor that already exists, on a licensed site, with the transmission already built, is the fastest way to add firm capacity anyone has found — and it still takes years.
Connecting a very large load usually means building something: a substation, a transmission upgrade, sometimes a line. That cost is real and somebody is assigned it. Every co-location dispute, every large-load rulemaking and every state proceeding on this subject is, underneath, an argument about who.
States have started writing the answer into the tariff rather than arguing it case by case. Georgia is the most developed example: the Public Service Commission ordered a base rate freeze through 2028 in July 2025, imposed minimum billing and longer contract terms on large loads, required new data center contracts to be filed thirty days before execution, and required Georgia Power to backstop the costs financially through 2031 if the contracts do not materialize.
Faced with four routes that are all slow or constrained, a great many developers took the most aggressive version of route 3: not co-locating beside somebody else's plant, but building their own generation on site and waiting for nobody. That generation is overwhelmingly natural gas, not nuclear, and it is happening now rather than in the 2030s. It is also the version of route 3 that genuinely adds supply, because the plant is new.
Even this has a queue of its own, just not a regulatory one. Gas turbines are sold out. As of manufacturer earnings reported in August 2026, GE Vernova held a 116 GW backlog with delivery slots into 2031; Siemens Energy quoted about three years and held 69 GW; Mitsubishi held 35 GW. Order intake is running three to seven times shipment rate, which is what a sold-out factory looks like.
The case for a small modular reactor next to a data center is a connection argument, not a generation argument. It is not that nuclear electricity is cheaper — it is not. It is that a reactor on your own site is route 3 in its supply-adding form, and it sidesteps both queues at once: no waiting for the grid to reach you, and no waiting for somebody else's plant to be built. It is the same argument that put gas turbines on eight campuses, with a different fuel.
That is a coherent argument. The difficulty is entirely in the present tense. As of August 2026, no small modular reactor is operating anywhere in the United States, and none is under construction with a data center as its contracted customer. The two most advanced construction permit applications in the country are TVA's Clinch River, for the Tennessee Valley grid, and X-energy's Long Mott, for a Dow chemical works at Seadrift, Texas. Neither is an AI project.
| Route | Time to first electricity | Adds supply? |
|---|---|---|
| Contract for an operating reactor | Months. The plant is already running | No |
| Restart a shut-down reactor | Years. Nothing has restarted yet in the US | Yes |
| Uprate an existing plant | Years, but the licence and connection exist | Yes |
| Build gas on site | Years, and turbine slots run into 2031 | Yes |
| Build a small modular reactor | Not yet demonstrated anywhere in the US | Yes |
This is why the sector's own scoreboard is worth watching more closely than its announcements. The thing that would change this picture is not another framework agreement. It is a construction permit application that names a data center as the customer, or an operating licence application from one of the companies already building. Neither had happened by August 2026.
Almost every misleading claim in this subject comes from describing one route in language borrowed from another. The decoder is short. When you read that a company is powering AI with some source of electricity, work out which of the four routes is being described, and then ask the question in the right-hand column.
| If the claim sounds like | It is probably | Ask |
|---|---|---|
| "We signed an agreement for X gigawatts" | Route 4, or nothing at all | Is there a named plant, a named seller and a stated term? Or is it a framework? |
| "We are building a plant to power our data centers" | Route 2 or 3 | Which regulatory instrument has been granted, and on what date? |
| "Powered by carbon-free energy" | Possibly attributes, not electricity | Do the electrons go to this company, or only the clean energy attributes? |
| "We will bypass the grid entirely" | Route 3, described as it was in 2024 | Which of the four co-located service products, and what is being paid? |
| "The grid cannot support this" | A connection claim, not a generation claim | Is the shortage energy, or capacity at the peak, or a wire that does not exist? |