Nuclear Power
The improvement

The fleet got a third bigger
without building anything.

Between 1980 and 2000 the US nuclear fleet went from producing barely half of what it could to nearly ninety percent of it, and almost no new reactors were built after 1990. That is the largest thing that has happened to American nuclear power in fifty years and it is rarely discussed. This page covers the fleet, what it costs, what happens to the waste, and who is actually building — with every number carrying its definition, because most of the disagreements in this subject are definitional.

Read this part
Every figure here carries its source and its date, and the date is part of the claim. This page deliberately shows disagreement between credible sources instead of resolving it, because in this subject most apparent disagreements are definitional and the definition is the useful part. Figures were checked in August 2026. Where a number could not be traced to a primary source it has been left out and said so, rather than filled in from a figure in circulation.
ON THIS PAGE
The World Fleet The US Fleet The Improvement Nobody Talks About Forty Years, Sixty, Eighty Shutdowns, and the Restarts That Have Not Happened What It Costs The Federal Push, and What 45U Actually Does Waste Policy Who Is Building, and Who Is Leaving Where This Comes From, and What Is Missing
And two slogans that have outlived their accuracy

The World Fleet

World, August 2026 Value
Operable power reactors 441 units
Net operable capacity About 404 GWe
Under construction 79 units
Planned 124 units, about 114 GWe
Generation, 2025 2,697 TWh, against 2,667 in 2024 and 2,601 in 2023
Share of world electricity About 9 percent
Countries operating nuclear power 31
Two figures that have become slogans
"Nuclear supplies 10 percent of world electricity" is a legacy figure from roughly 2010 to 2015. It has been in the 9 percent band for a decade. "About 440 reactors" happens to be right at the moment, at 441 — but it has been repeated continuously since about 2012, through periods when the true count was 435 and when it was 448. It is a slogan that is occasionally also a citation.
Country Operable reactors Note
United States 94 By the World Nuclear Association count. The NRC says 95 and EIA says 96 — see the next section
China 64 And 37 of the world’s 79 units under construction
France 57 The highest nuclear share of any national grid
Russia 34
Japan 33 Read carefully. This counts units not formally declared permanently shut, including several that have not generated since 2011 and have no realistic restart path

The construction picture is the part most often described as a global renaissance and is better described as a Chinese one. China alone accounts for 37 of the 79 units under construction worldwide, about 47 percent by unit count. Add India, Russia, South Korea, Turkey and Egypt and the top six reach 64 of 79, about 81 percent. Everything else on Earth — all of Europe, both Americas, the rest of Asia and Africa combined — accounts for fifteen units. In the United States the figure is zero, and has been since Vogtle 4 finished.

Four institutions, four counts, and all of them defensible

The US Fleet

How many reactors does the United States operate? Four institutions, four answers, all of them defensible. They are counting different things. NRC Aug 2026 95 Licensed reactor units authorized to operate EIA, Electric Power Annual Mar 2026 96 Generators, not reactors. A unit driving two turbine-generators counts twice EIA, Monthly Energy Review Jun 2026 94 Operable reactor units. EIA disagreeing with EIA by two WNA, DOE-NE, NEI Jul 2026 94 Units actually available to generate Before quoting a fleet number, decide whether you mean licensed units, generators, or units able to generate.
The same fleet counted four ways in 2026. NRC counts licensed reactor units; EIA's Electric Power Annual counts generators, so a unit driving two turbine-generator sets is counted twice; EIA's own Monthly Energy Review counts operable units and disagrees with the Electric Power Annual by two; the trade and industry counts track units actually available to generate. No bars, because a two percent spread drawn on a suppressed zero would misrepresent the size of the disagreement.

The mechanical cause of the EIA-versus-NRC gap is that EIA's electric power surveys collect on Form EIA-860 at the generator level while the NRC licenses reactor units. A wrinkle specific to 2026 makes it worse: Palisades now appears on the NRC's operating list while producing no electricity, so any count including it overstates generating capability by 789 MWe, and any capacity factor computed with it in the denominator is depressed.

And the capacity figure has the same problem
98,441 MW EIA Nuclear explained, described as net summer capacity, March 2026. Pairs with the 96-generator count. Net summer
103,581 MW EIA Electric Power Annual Table 4.3 nameplate for 2024. This is the number people are rounding when they say "about 100 GW". Nameplate
94,048 MW EIA Monthly Energy Review, June 2026. Pairs with the 94-unit series, and is the outlier. Operable units

"About 100 GW of US nuclear capacity" is either the nameplate figure rounded down or the net summer figure rounded up, and the distinction is worth about five percent. State which series you mean.

Largest and smallest, which is two questions
Largest single reactor: Grand Gulf, Mississippi, about 1,400 MW net summer. Largest site: Vogtle, Georgia, four units — which took the title from Palo Verde when Unit 4 finished in 2024. Smallest operating reactors: the two Prairie Island units in Minnesota, about 520 MW each. Smallest site: R. E. Ginna, New York, a single unit. "Grand Gulf is the largest US nuclear plant" and "Vogtle is the largest US nuclear plant" are both in circulation and both defensible only under a stated definition.
The US fleet got a third larger without building anything

The Improvement Nobody Talks About

Between 1980 and 2000 the US nuclear fleet went from producing barely more than half of what it was capable of to producing nearly ninety percent of it. No new reactors were needed for that, and after about 1990 essentially none were built. It is the largest single source of US nuclear output growth in fifty years and it is almost never discussed.

The US fleet got a third bigger without building anything Fleet capacity factor, percent. Installed capacity has been roughly flat since 1990. Nuclear Energy Institute series and EIA Electric Power Annual Table 4.08.B 40% 60% 80% 100% 1971 1980 1990 2000 2010 2020 2025 56% 88% 93% What it means A fleet running at 56% and one running at 92% differ by two thirds of their own output. The US built almost no new reactors after 1990 and still produced far more nuclear electricity in 2020 than in 1990.
US nuclear fleet capacity factor, 1971 to 2025, from the Nuclear Energy Institute series and EIA Electric Power Annual Table 4.08.B. Installed capacity has been roughly flat near 100 GW since 1990. The record year was 2019 at 93.4 percent.

How it was done is not mysterious and it is not a single trick: outage duration management, moving from twelve-month to eighteen- and twenty-four-month fuel cycles, condition-based maintenance, equipment reliability programmes, and the operational discipline that followed Three Mile Island. A fleet running at 56 percent and one running at 92 percent differ by two thirds of their own output. The United States built almost no new reactors after 1990 and still produced far more nuclear electricity in 2020 than in 1990.

Uprates did the rest
The NRC has approved 172 power uprate applications totalling about 8,030 MWe, in three categories: measurement uncertainty recapture, typically under two percent from better feedwater flow instrumentation; stretch uprates within existing design margins, typically up to seven percent; and extended uprates above that, which need turbines, generators and feedwater heaters replaced. Eight thousand megawatts is about eight percent of current net summer capacity — roughly seven AP1000s — obtained without a single construction permit. NRC notes its own figure excludes capacity recapture uprates granted between 1969 and 1990, so the true historical total is higher.
License renewal is now the main event in US nuclear

Forty Years, Sixty, Eighty

US operating licenses were originally issued for 40 years — a term set by antitrust and amortisation considerations rather than by any engineering limit on plant life. Renewal adds 20 years at a time, subject to an aging management review that has to demonstrate the license renewal commitments are met for the extended period.

  1. 1
    Initial license renewal, 40 to 60 years
    Now routine. The great majority of the operating fleet has been through it, and the review is a well-trodden process rather than a novel undertaking.
  2. 2
    Subsequent license renewal, 60 to 80 years
    As of August 2026 the NRC had approved 13 applications covering 25 reactor units at 13 sites — Turkey Point, Peach Bottom, Surry, North Anna, Point Beach, Oconee, St. Lucie, Monticello, Summer and others — with seven of those approvals issued in the eighteen months to June 2026. Note that at least one widely cited secondary source gives a substantially lower number; the NRC's own table is the one to use.
  3. 3
    Beyond eighty years
    No US plant has been licensed past 80 years. The technical questions are concrete rather than philosophical: reactor pressure vessel embrittlement, concrete containment degradation, cable qualification, and irradiation-assisted stress corrosion cracking in core internals. These are being studied; they are not settled.

This matters commercially as much as technically. A plant that has just been licensed to 80 years is a plant with decades of amortisation left, which is the background condition for every power purchase agreement being signed with a technology company — and it is why the recent capital expenditure cycle shows up in the fleet's cost data.

Thirteen closures, then a reversal, and so far no reactor back on the grid

Shutdowns, and the Restarts That Have Not Happened

Between 2013 and 2022 a wave of US reactors closed. The dominant cause was economic: sustained low natural gas prices after 2008, combined with energy-only merchant market designs that paid nothing for firm capacity or for zero-carbon attributes. Single-unit merchant plants in restructured markets were the vulnerable class, being sub-scale on fixed operations and maintenance cost per megawatt-hour with no rate base to fall back on.

Then it stopped. No US reactor has permanently shut down since Palisades in May 2022. The 45U production tax credit, state zero-emission credit programmes and data centre load growth between them removed the economic case for further closures — and three of the recent closures are now being reversed.

The restart status, stated precisely
As of August 2026 no US power reactor restart has been completed. No restarted unit has achieved criticality, grid synchronisation or resumption of commercial operation. Palisades is the furthest along and the one most likely to be misreported: the NRC restored its power-operation licensing basis on 24 July 2025, changed its status from decommissioning to restarting on 9 September 2025, and it now appears on the NRC's operating list — while generating zero. Crane Clean Energy Center, the former Three Mile Island Unit 1, and Duane Arnold are both still in SAFSTOR at an earlier stage. A plant appearing on an operating list is a licensing fact, not a generation fact.
Two numbers that are both true and are not comparable

What It Costs

New build, EIA AEO2026 levelized cost 2025 $/MWh
Onshore wind 56.75
Solar PV, standalone 58.33
Geothermal 64.77
Natural gas combined cycle 77.46
Advanced nuclear 87.81
Offshore wind 118.79
Battery storage, as levelized cost of storage 152.61
EIA’s own warning about its own table
EIA states plainly that "direct comparisons of LCOE or LCOS across technologies are misleading as a method to assess the economic competitiveness". The insistence on pairing levelized cost with levelized avoided cost is not boilerplate: the nuclear-to-solar gap compares a roughly 90 percent capacity factor dispatchable resource with a roughly 25 percent capacity factor variable one whose marginal value falls as penetration rises. Presenting the table as "nuclear costs half again what wind costs" is exactly the use EIA says is misleading.
Running an old plant against building a new one
$36.46 per MWh Total generating cost of the existing US fleet in 2025 — fuel $5.95, sustaining capital $9.69, operating $20.82. Down about 35 percent since 2012, but up 5.1 percent year on year in 2025 on a 24 percent rise in capital spend. Existing
$87.81 per MWh Levelized cost of advanced nuclear entering service in 2031, in 2025 dollars, dominated by overnight construction cost. New build

Concluding that existing nuclear is 2.4 times cheaper than new nuclear is directionally true and numerically meaningless. The first figure excludes the sunk construction cost entirely; the second is mostly that cost. Note too the 2025 inflection: after thirteen years of decline the fleet cost curve turned up on capital expenditure, which is what a subsequent license renewal and uprate investment cycle looks like in the accounts.

Vogtle 3 and 4 are the American data point for new build, and they are sobering. Construction began in 2009 with Unit 3 planned for 2016 and Unit 4 for 2017, at an estimated $14 billion. Unit 3 entered commercial operation in July 2023 and Unit 4 in April 2024, at a project cost EIA puts at more than $30 billion — about 2.2 times the estimate, roughly seven years late, and fifteen years of construction for a project planned at seven. Figures of $35 and $36 billion also circulate; those generally fold in financing, owner's costs, or the Westinghouse bankruptcy settlement, which sat outside the construction budget.

The credit everyone describes as a subsidy is a price floor

The Federal Push, and What 45U Actually Does

The Inflation Reduction Act created a zero-emission nuclear power production credit at 26 U.S.C. § 45U, for plants placed in service before 16 August 2022 — new build is excluded by design. It terminates for electricity produced after 31 December 2032. It is almost universally reported as a $15 per megawatt-hour subsidy for nuclear plants, and that description is wrong in a way that matters.

  1. 1
    The base credit
    0.3 cents per kilowatt-hour, or $3.00/MWh, rising to 1.5 cents per kilowatt-hour — $15.00/MWh — where prevailing wage and apprenticeship requirements are met. Both figures are indexed for inflation from a 2023 base, so the statutory numbers are not the current numbers.
  2. 2
    The clawback nobody mentions
    The credit is reduced by 16 percent of the excess of gross receipts over 2.5 cents per kilowatt-hour, which with the multiplier works out at about 80 percent of that excess — and state zero-emission credit payments count toward gross receipts.
  3. 3
    So what it really is
    The credit phases out entirely once realised revenue reaches roughly 4.375 cents per kilowatt-hour. It is a revenue floor of about $43.75/MWh, not a per megawatt-hour payment. A plant selling at $50/MWh receives nothing. A plant at $30/MWh receives close to the full amount. In the high-price environment of 2024 to 2026, many merchant units have received little or none of it.

Alongside the credit, the Department of Energy has moved substantial money: an SMR funding round, a reactor pilot programme with nine selected vendors, a strategic partnership with Westinghouse aimed at AP1000 and AP300 deployment, a loan package to Southern Company described as the largest in DOE loan programme history, conditional commitments across five projects of two AP1000 units each, supply chain financing, and an uprate support package covering 345 MWe across six reactors. Several of those headline figures reach the public through secondary reporting rather than DOE primary documents; for anything consequential, verify the announcement itself.

A technical problem that was solved and a political problem that was not

Waste Policy

US commercial spent fuel inventory was about 86,000 tonnes at 75 sites in 33 states when GAO counted in 2021, and DOE put it near 90,000 tonnes shortly afterwards; it accumulates at roughly 2,000 tonnes a year. On that trajectory the 2026 figure should be somewhere near 95,000 to 96,000 tonnes, but no source reachable for this page publishes a current number. The 86,000 tonne figure is a 2021 number and is now roughly ten thousand tonnes low, which does not stop it being quoted as current.

And the NRC gives two answers on dry storage
68 general plus 17 specific NRC dry cask storage fact sheet, January 2023: dry storage in 37 states at 68 sites under general licenses and 17 with specific licenses. 85 total
48 general plus 15 specific NRC spent fuel storage FAQs, October 2024: of currently licensed ISFSIs, 48 operate under general licenses and 15 have specific licenses. 63 total

Two NRC pages, twenty sites apart, and the later page gives the smaller number, so this is not growth over time. The likely reconciliation is that one counts sites where dry storage exists and the other counts currently licensed ISFSIs, but neither page defines its terms. Cite the page, the date and the wording rather than the number alone. A national cask count could not be sourced at all; figures around four thousand circulate and are not reproduced here.

Yucca Mountain, stated precisely
This is the item most often described sloppily. DOE submitted the license application on 3 June 2008. It was never withdrawn — DOE moved to withdraw it with prejudice in 2010 and did not succeed in removing it from the docket. The NRC staff's Safety Evaluation Report, NUREG-1949, was completed in five volumes with the final ones published in January 2015, and Volume 3 concluded that the proposed repository meets the 10 CFR Part 63 Subpart L limits for individual protection, human intrusion and groundwater protection. A supplemental environmental impact statement followed in May 2016. Whatever one thinks of the site, it is not true that a negative safety finding stopped it.

The money has an odd shape too. The Nuclear Waste Policy Act fee of one mill per kilowatt-hour has been set at zero since 16 May 2014, after the D.C. Circuit ordered DOE to justify a fee it could not justify without a repository programme. Meanwhile the government is in breach of the Standard Contract for failing to take title to the fuel, and had paid reactor owners about $9 billion in damages as of GAO's 2021 count, with the figure growing annually. Those damages come out of the Treasury's Judgment Fund rather than the Nuclear Waste Fund, so the growing liability does not draw down the fund and does not appear as a nuclear programme cost anywhere obvious.

Internationally the picture is different. Finland's Onkalo is the furthest advanced deep geological repository anywhere. As of August 2026 it had completed its first full-scale trial canister emplacement in June 2026 and cleared the regulator's safety assessment in August, but the government operating licence had not been granted. It has not "opened", and reports that it has are ahead of the record.

Including the phase-outs that have started to reverse

Who Is Building, and Who Is Leaving

Of 79 reactors under construction worldwide, China has 37. It is not a global construction boom with a Chinese component; it is a Chinese construction boom with a global remainder. China has been approving around ten units a year and has been completing them close to schedule and close to budget, which is the part of the story most relevant to anyone arguing about whether nuclear construction cost is a law of nature or a consequence of having stopped doing it.

Country Position, 2026
China 37 units under construction, and a serial build programme
India 8 under construction
Russia 7 at home, and the largest export order book
South Korea, Turkey, Egypt 4 each — Turkey and Egypt are Russian-built
United States Zero under construction since Vogtle 4 finished, alongside the largest federal financing effort in decades
Germany Phase-out completed in April 2023

The phase-out story is no longer moving in one direction. Several countries that legislated an exit have softened, delayed or reversed it since 2022, driven by energy security after the invasion of Ukraine and by decarbonisation targets that proved hard to meet without firm low-carbon generation. Germany's exit was completed and has not been reversed. Others have been revisited. If you are citing a national phase-out policy, check its date — this is the fastest moving part of the subject and several widely repeated positions are two or three years out of date.

Including the figures this page declined to give

Where This Comes From, and What Is Missing

What this page does not tell you, on purpose
Three figures a reader might reasonably want are absent because they could not be traced to a primary source: the total collected into the Nuclear Waste Fund and its current balance, DOE's estimated future liability for failing to take title to spent fuel, and the national count of loaded dry storage casks. Figures in circulation for all three are easy to find and have deliberately not been reproduced here. They are recoverable from GAO's audits of DOE's financial statements, DOE's annual financial report, and the Court of Federal Claims spent fuel docket.